Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $171k | 15k |
MMBtu
|
$11.03 |
- Electrical | $102k | 1,235k |
kWh
|
$0.089 |
- Natural Gas | $20k | 2.6k |
MMBtu
|
$7.14 |
139
Recommendations
6.0
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $72k | 5.9k |
MMBtu
|
38.7% |
- Electrical | $48k | 577k |
kWh
|
46.7% |
- Natural Gas | $4.7k | - |
MMBtu
|
- |
Waste | $0.5k | |||
Productivity/Other | $5.5k | |||
TOTAL | $78k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
17
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $106k | 11k |
MMBtu
|
$10.95 |
- Electrical | $62k | 781k |
kWh
|
$0.094 |
- Natural Gas | $22k | 2.8k |
MMBtu
|
$7.77 |
43
Implemented Recommendations
2.5
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $13k | 1.0k |
MMBtu
|
9.0% |
- Electrical | $7.0k | 95k |
kWh
|
12.1% |
- Natural Gas | $2.6k | - |
MMBtu
|
- |
Waste | $0.5k | |||
Productivity/Other | $1.9k | |||
TOTAL | $16k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |