The ITAC Statistics page displays the average assessment results for the selected criteria.
5
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $1,410k | 201k |
MMBtu
|
$6.92 |
- Electrical | $1,017k | 14,423k |
kWh
|
$0.060 |
- Natural Gas | $336k | 53k |
MMBtu
|
$4.95 |
57
Recommendations
11.4
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $262k | 21k |
MMBtu
|
10.6% |
- Electrical | $156k | 2,067k |
kWh
|
14.3% |
- Natural Gas | $102k | - |
MMBtu
|
- |
Waste | $3.4k | |||
Productivity/Other | $28k | |||
TOTAL | $294k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
3
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $2,220k | 316k |
MMBtu
|
$6.91 |
- Electrical | $1,634k | 22,919k |
kWh
|
$0.063 |
- Natural Gas | $518k | 81k |
MMBtu
|
$4.19 |
17
Implemented Recommendations
5.7
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $168k | 6.4k |
MMBtu
|
2.0% |
- Electrical | $42k | 626k |
kWh
|
2.7% |
- Natural Gas | $124k | - |
MMBtu
|
- |
Waste | - | |||
Productivity/Other | ($-3.1)k | |||
TOTAL | $165k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |