ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
SIC 5141 Groceries, general line

4

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $246k 38k
MMBtu
$7.17
- Electrical $180k 3,350k
kWh
$0.058
- Natural Gas $20k 4.1k
MMBtu
$12.00

29

Recommendations

7.3

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $39k 5.5k
MMBtu
14.2%
- Electrical $33k 533k
kWh
15.9%
- Natural Gas $0.2k -
MMBtu
-
Waste -
Productivity/Other $0.4k
TOTAL $40k
*May be negative reflecting an increased cost component required to save energy and costs overall

3

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $249k 43k
MMBtu
$6.29
- Electrical $168k 3,700k
kWh
$0.046
- Natural Gas $25k 5.2k
MMBtu
$13.56

9

Implemented Recommendations

3.0

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $2.3k 0.4k
MMBtu
0.8%
- Electrical $1.7k 35k
kWh
1.0%
- Natural Gas $0.0k -
MMBtu
-
Waste -
Productivity/Other -
TOTAL $2.3k
*May be negative reflecting an increased cost component required to save energy and costs overall