The ITAC Statistics page displays the average assessment results for the selected criteria.
| ARC | 2+ Digits Required | |
| NAICS | 3+ Digits Required | |
| SIC | Scrap and waste materials | |
| 3+ Characters Required for Products | ||
3
Matching Assessments
| Initial Plant Size Averages | Costs | Usage | Unit Cost | |
|---|---|---|---|---|
| All Energy | $1,113k | 167k |
MMBtu
|
$11.54 |
| - Electrical | $468k | 15,525k |
kWh
|
$0.060 |
| - Natural Gas | $19k | 3.9k |
MMBtu
|
$1.65 |
20
Recommendations
6.7
Recommendations Per Assessment
| Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
|---|---|---|---|---|
| All Energy | $181k | 14k |
MMBtu
|
8.6% |
| - Electrical | $127k | 1,404k |
kWh
|
9.0% |
| - Natural Gas | $9.6k | - |
MMBtu
|
- |
| Waste | $6.3k | |||
| Productivity/Other | - | |||
| TOTAL | $188k | |||
| *May be negative reflecting an increased cost component required to save energy and costs overall | ||||
2
with Implementation Data
| Initial Plant Size Averages | Costs | Usage | Unit Cost | |
|---|---|---|---|---|
| All Energy | $1,552k | 244k |
MMBtu
|
$8.13 |
| - Electrical | $691k | 23,186k |
kWh
|
$0.036 |
| - Natural Gas | $29k | 5.9k |
MMBtu
|
$2.48 |
3
Implemented Recommendations
1.5
Implemented Per Assessment
| Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
|---|---|---|---|---|
| All Energy | $13k | 0.1k |
MMBtu
|
0.0% |
| - Electrical | $0.3k | 6.9k |
kWh
|
0.0% |
| - Natural Gas | - | - |
MMBtu
|
- |
| Waste | - | |||
| Productivity/Other | - | |||
| TOTAL | $13k | |||
| *May be negative reflecting an increased cost component required to save energy and costs overall | ||||