ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Automobiles and other motor vehicles
3+ Characters Required for Products

1

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $92k 13k
MMBtu
$7.23
- Electrical $63k 792k
kWh
$0.079
- Natural Gas $29k 4.6k
MMBtu
$6.40

9

Recommendations

9.0

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $38k 3.9k
MMBtu
30.7%
- Electrical $29k 381k
kWh
48.1%
- Natural Gas $9.0k -
MMBtu
-
Waste -
Productivity/Other -
TOTAL $38k
*May be negative reflecting an increased cost component required to save energy and costs overall

1

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $92k 13k
MMBtu
$7.23
- Electrical $63k 792k
kWh
$0.079
- Natural Gas $29k 4.6k
MMBtu
$6.40

3

Implemented Recommendations

3.0

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $11k 0.4k
MMBtu
3.0%
- Electrical $3.0k 37k
kWh
4.7%
- Natural Gas $7.7k -
MMBtu
-
Waste -
Productivity/Other -
TOTAL $11k
*May be negative reflecting an increased cost component required to save energy and costs overall