The ITAC Statistics page displays the average assessment results for the selected criteria.
35
Matching Assessments
| Initial Plant Size Averages | Costs | Usage | Unit Cost | |
|---|---|---|---|---|
| All Energy | $575k | 102k |
MMBtu
|
$10.55 |
| - Electrical | $319k | 5,136k |
kWh
|
$0.10 |
| - Natural Gas | $100k | 49k |
MMBtu
|
$5.90 |
255
Recommendations
7.3
Recommendations Per Assessment
| Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
|---|---|---|---|---|
| All Energy | $63k | 6.5k |
MMBtu
|
6.4% |
| - Electrical | $38k | 635k |
kWh
|
12.4% |
| - Natural Gas | $10k | - |
MMBtu
|
- |
| Waste | $2.0k | |||
| Productivity/Other | $16k | |||
| TOTAL | $81k | |||
| *May be negative reflecting an increased cost component required to save energy and costs overall | ||||
31
with Implementation Data
| Initial Plant Size Averages | Costs | Usage | Unit Cost | |
|---|---|---|---|---|
| All Energy | $597k | 109k |
MMBtu
|
$10.80 |
| - Electrical | $328k | 5,242k |
kWh
|
$0.11 |
| - Natural Gas | $109k | 55k |
MMBtu
|
$5.83 |
118
Implemented Recommendations
3.8
Implemented Per Assessment
| Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
|---|---|---|---|---|
| All Energy | $27k | 3.2k |
MMBtu
|
2.9% |
| - Electrical | $15k | 312k |
kWh
|
5.9% |
| - Natural Gas | $4.7k | - |
MMBtu
|
- |
| Waste | $0.9k | |||
| Productivity/Other | $1.1k | |||
| TOTAL | $29k | |||
| *May be negative reflecting an increased cost component required to save energy and costs overall | ||||