ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Wholesale trade-durable goods
3+ Characters Required for Products

32

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $588k 107k
MMBtu
$10.65
- Electrical $324k 5,238k
kWh
$0.10
- Natural Gas $106k 53k
MMBtu
$6.21

240

Recommendations

7.5

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $66k 6.9k
MMBtu
6.4%
- Electrical $39k 669k
kWh
12.8%
- Natural Gas $11k -
MMBtu
-
Waste $2.1k
Productivity/Other $12k
TOTAL $81k
*May be negative reflecting an increased cost component required to save energy and costs overall

30

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $599k 112k
MMBtu
$10.44
- Electrical $337k 5,391k
kWh
$0.11
- Natural Gas $112k 56k
MMBtu
$5.62

109

Implemented Recommendations

3.6

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $27k 3.3k
MMBtu
2.9%
- Electrical $15k 318k
kWh
5.9%
- Natural Gas $4.1k -
MMBtu
-
Waste $1.0k
Productivity/Other $1.2k
TOTAL $29k