The ITAC Statistics page displays the average assessment results for the selected criteria.
5
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $3,877k | 508k |
MMBtu
|
$10.49 |
- Electrical | $1,909k | 44,136k |
kWh
|
$0.066 |
- Natural Gas | $276k | 52k |
MMBtu
|
$4.92 |
36
Recommendations
7.2
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $85k | 16k |
MMBtu
|
3.2% |
- Electrical | $74k | 1,604k |
kWh
|
3.6% |
- Natural Gas | $7.8k | - |
MMBtu
|
- |
Waste | - | |||
Productivity/Other | $0.2k | |||
TOTAL | $85k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
5
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $3,877k | 508k |
MMBtu
|
$10.49 |
- Electrical | $1,909k | 44,136k |
kWh
|
$0.066 |
- Natural Gas | $276k | 52k |
MMBtu
|
$4.92 |
13
Implemented Recommendations
2.6
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $55k | 13k |
MMBtu
|
2.5% |
- Electrical | $54k | 1,252k |
kWh
|
2.8% |
- Natural Gas | - | - |
MMBtu
|
- |
Waste | - | |||
Productivity/Other | $0.0k | |||
TOTAL | $55k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |