ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Motor freight transportation and warehousing
3+ Characters Required for Products

33

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $714k 67k
MMBtu
$12.73
- Electrical $351k 4,339k
kWh
$0.095
- Natural Gas $124k 20k
MMBtu
$3.85

210

Recommendations

6.4

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $129k 7.6k
MMBtu
11.3%
- Electrical $70k 739k
kWh
17.0%
- Natural Gas $20k -
MMBtu
-
Waste $0.2k
Productivity/Other $23k
TOTAL $153k
*May be negative reflecting an increased cost component required to save energy and costs overall

21

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $455k 62k
MMBtu
$9.39
- Electrical $184k 3,100k
kWh
$0.077
- Natural Gas $184k 30k
MMBtu
$3.26

71

Implemented Recommendations

3.4

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $27k 3.4k
MMBtu
5.4%
- Electrical $20k 327k
kWh
10.5%
- Natural Gas $2.0k -
MMBtu
-
Waste -
Productivity/Other $15k
TOTAL $42k
*May be negative reflecting an increased cost component required to save energy and costs overall