ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Signs and advertising specialties
3+ Characters Required for Products

46

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $199k 29k
MMBtu
$7.76
- Electrical $115k 2,133k
kWh
$0.065
- Natural Gas $39k 7.0k
MMBtu
$5.72

350

Recommendations

7.6

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $35k 3.8k
MMBtu
13.1%
- Electrical $23k 369k
kWh
17.3%
- Natural Gas $6.0k -
MMBtu
-
Waste $2.3k
Productivity/Other $12k
TOTAL $50k
*May be negative reflecting an increased cost component required to save energy and costs overall

45

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $197k 29k
MMBtu
$7.69
- Electrical $113k 2,139k
kWh
$0.064
- Natural Gas $39k 7.0k
MMBtu
$5.58

150

Implemented Recommendations

3.3

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $13k 0.9k
MMBtu
3.1%
- Electrical $7.6k 89k
kWh
4.2%
- Natural Gas $3.3k -
MMBtu
-
Waste $0.2k
Productivity/Other $3.0k
TOTAL $16k
*May be negative reflecting an increased cost component required to save energy and costs overall