ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Miscellaneous manufacturing industries
3+ Characters Required for Products

196

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $706k 116k
MMBtu
$8.56
- Electrical $377k 7,123k
kWh
$0.072
- Natural Gas $211k 41k
MMBtu
$6.25

1,460

Recommendations

7.4

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $79k 9.8k
MMBtu
8.5%
- Electrical $44k 959k
kWh
13.5%
- Natural Gas $21k -
MMBtu
-
Waste $1.7k
Productivity/Other $27k
TOTAL $109k
*May be negative reflecting an increased cost component required to save energy and costs overall

190

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $721k 119k
MMBtu
$8.48
- Electrical $384k 7,291k
kWh
$0.071
- Natural Gas $217k 42k
MMBtu
$6.19

643

Implemented Recommendations

3.4

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $28k 2.3k
MMBtu
2.0%
- Electrical $14k 228k
kWh
3.1%
- Natural Gas $10k -
MMBtu
-
Waste $0.5k
Productivity/Other $6.2k
TOTAL $34k
*May be negative reflecting an increased cost component required to save energy and costs overall