The ITAC Statistics page displays the average assessment results for the selected criteria.
9
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $241k | 49k |
MMBtu
|
$6.85 |
- Electrical | $140k | 3,215k |
kWh
|
$0.051 |
- Natural Gas | $34k | 15k |
MMBtu
|
$5.70 |
65
Recommendations
7.2
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $43k | 5.0k |
MMBtu
|
10.2% |
- Electrical | $26k | 490k |
kWh
|
15.2% |
- Natural Gas | $5.5k | - |
MMBtu
|
- |
Waste | $6.6k | |||
Productivity/Other | $3.4k | |||
TOTAL | $53k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
9
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $241k | 49k |
MMBtu
|
$6.85 |
- Electrical | $140k | 3,215k |
kWh
|
$0.051 |
- Natural Gas | $34k | 15k |
MMBtu
|
$5.70 |
30
Implemented Recommendations
3.3
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $17k | 1.8k |
MMBtu
|
3.7% |
- Electrical | $13k | 176k |
kWh
|
5.5% |
- Natural Gas | $2.2k | - |
MMBtu
|
- |
Waste | $6.1k | |||
Productivity/Other | $3.2k | |||
TOTAL | $26k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |