The ITAC Statistics page displays the average assessment results for the selected criteria.
| ARC | 2+ Digits Required | |
| NAICS | 3+ Digits Required | |
| SIC | Guided missiles and space vehicles | |
| 3+ Characters Required for Products | ||
3
Matching Assessments
| Initial Plant Size Averages | Costs | Usage | Unit Cost | |
|---|---|---|---|---|
| All Energy | $1,340k | 158k |
MMBtu
|
$7.93 |
| - Electrical | $896k | 12,131k |
kWh
|
$0.073 |
| - Natural Gas | $189k | 34k |
MMBtu
|
$7.70 |
26
Recommendations
8.7
Recommendations Per Assessment
| Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
|---|---|---|---|---|
| All Energy | $250k | 25k |
MMBtu
|
16.0% |
| - Electrical | $213k | 2,474k |
kWh
|
20.4% |
| - Natural Gas | ($-2.0)k | - |
MMBtu
|
- |
| Waste | - | |||
| Productivity/Other | $1.5k | |||
| TOTAL | $252k | |||
| *May be negative reflecting an increased cost component required to save energy and costs overall | ||||
2
with Implementation Data
| Initial Plant Size Averages | Costs | Usage | Unit Cost | |
|---|---|---|---|---|
| All Energy | $606k | 73k |
MMBtu
|
$7.63 |
| - Electrical | $555k | 6,729k |
kWh
|
$0.075 |
| - Natural Gas | $20k | 4.1k |
MMBtu
|
$8.75 |
8
Implemented Recommendations
4.0
Implemented Per Assessment
| Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
|---|---|---|---|---|
| All Energy | $147k | 14k |
MMBtu
|
19.1% |
| - Electrical | $137k | 1,364k |
kWh
|
20.3% |
| - Natural Gas | $0.8k | - |
MMBtu
|
- |
| Waste | - | |||
| Productivity/Other | ($-0.3)k | |||
| TOTAL | $147k | |||
| *May be negative reflecting an increased cost component required to save energy and costs overall | ||||