ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Guided missiles and space vehicles and parts
3+ Characters Required for Products

20

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $977k 137k
MMBtu
$8.23
- Electrical $423k 8,454k
kWh
$0.064
- Natural Gas $349k 46k
MMBtu
$5.59

145

Recommendations

7.3

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $175k 14k
MMBtu
10.6%
- Electrical $90k 1,408k
kWh
16.7%
- Natural Gas $47k -
MMBtu
-
Waste $0.2k
Productivity/Other $86k
TOTAL $261k
*May be negative reflecting an increased cost component required to save energy and costs overall

19

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $978k 139k
MMBtu
$8.09
- Electrical $398k 8,451k
kWh
$0.062
- Natural Gas $367k 48k
MMBtu
$5.18

66

Implemented Recommendations

3.5

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $42k 2.1k
MMBtu
1.5%
- Electrical $17k 206k
kWh
2.4%
- Natural Gas $24k -
MMBtu
-
Waste $0.1k
Productivity/Other $69k
TOTAL $110k
*May be negative reflecting an increased cost component required to save energy and costs overall