ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Motorcycles, bicycles, and parts
3+ Characters Required for Products

8

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $171k 15k
MMBtu
$10.96
- Electrical $105k 1,132k
kWh
$0.092
- Natural Gas $20k 3.4k
MMBtu
$7.14

55

Recommendations

6.9

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $19k 1.4k
MMBtu
9.4%
- Electrical $13k 138k
kWh
12.2%
- Natural Gas $1.6k -
MMBtu
-
Waste $4.3k
Productivity/Other $25k
TOTAL $48k
*May be negative reflecting an increased cost component required to save energy and costs overall

8

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $171k 15k
MMBtu
$10.96
- Electrical $105k 1,132k
kWh
$0.092
- Natural Gas $20k 3.4k
MMBtu
$7.14

23

Implemented Recommendations

2.9

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $6.0k 0.5k
MMBtu
3.3%
- Electrical $4.5k 48k
kWh
4.3%
- Natural Gas $0.3k -
MMBtu
-
Waste $3.1k
Productivity/Other $20k
TOTAL $29k
*May be negative reflecting an increased cost component required to save energy and costs overall