ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Railroad equipment
3+ Characters Required for Products

3

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $1,155k 200k
MMBtu
$6.30
- Electrical $869k 13,328k
kWh
$0.075
- Natural Gas $200k 63k
MMBtu
$2.02

22

Recommendations

7.3

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $99k 14k
MMBtu
7.2%
- Electrical $90k 1,397k
kWh
10.5%
- Natural Gas $8.9k -
MMBtu
-
Waste -
Productivity/Other $5.7k
TOTAL $105k
*May be negative reflecting an increased cost component required to save energy and costs overall

2

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $512k 83k
MMBtu
$6.63
- Electrical $436k 5,257k
kWh
$0.083
- Natural Gas $76k 29k
MMBtu
$1.33

10

Implemented Recommendations

5.0

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $12k 0.7k
MMBtu
0.8%
- Electrical $5.6k 68k
kWh
1.3%
- Natural Gas $6.9k -
MMBtu
-
Waste -
Productivity/Other $9.4k
TOTAL $22k
*May be negative reflecting an increased cost component required to save energy and costs overall