ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Aircraft and parts
3+ Characters Required for Products

359

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $600k 81k
MMBtu
$8.86
- Electrical $366k 6,279k
kWh
$0.13
- Natural Gas $84k 15k
MMBtu
$6.17

2,627

Recommendations

7.3

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $83k 7.9k
MMBtu
9.7%
- Electrical $54k 769k
kWh
12.2%
- Natural Gas $6.9k -
MMBtu
-
Waste $4.1k
Productivity/Other $31k
TOTAL $119k
*May be negative reflecting an increased cost component required to save energy and costs overall

340

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $604k 83k
MMBtu
$8.65
- Electrical $371k 6,409k
kWh
$0.13
- Natural Gas $87k 16k
MMBtu
$6.05

1,152

Implemented Recommendations

3.4

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $29k 2.8k
MMBtu
3.4%
- Electrical $19k 274k
kWh
4.3%
- Natural Gas $1.9k -
MMBtu
-
Waste $2.4k
Productivity/Other $15k
TOTAL $46k
*May be negative reflecting an increased cost component required to save energy and costs overall