ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Semiconductors and related devices
3+ Characters Required for Products

84

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $1,084k 171k
MMBtu
$7.90
- Electrical $750k 14,809k
kWh
$0.065
- Natural Gas $130k 18k
MMBtu
$6.93

618

Recommendations

7.4

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $107k 11k
MMBtu
6.6%
- Electrical $68k 1,094k
kWh
7.4%
- Natural Gas $17k -
MMBtu
-
Waste $4.3k
Productivity/Other $85k
TOTAL $197k
*May be negative reflecting an increased cost component required to save energy and costs overall

76

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $1,076k 176k
MMBtu
$7.66
- Electrical $739k 15,325k
kWh
$0.064
- Natural Gas $123k 18k
MMBtu
$6.81

246

Implemented Recommendations

3.2

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $23k 2.6k
MMBtu
1.5%
- Electrical $15k 258k
kWh
1.7%
- Natural Gas $4.3k -
MMBtu
-
Waste $2.3k
Productivity/Other $5.2k
TOTAL $30k
*May be negative reflecting an increased cost component required to save energy and costs overall