ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Semiconductors and related devices
3+ Characters Required for Products

86

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $1,064k 167k
MMBtu
$7.99
- Electrical $736k 14,502k
kWh
$0.067
- Natural Gas $127k 18k
MMBtu
$6.98

627

Recommendations

7.3

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $106k 11k
MMBtu
6.6%
- Electrical $67k 1,074k
kWh
7.4%
- Natural Gas $17k -
MMBtu
-
Waste $4.2k
Productivity/Other $83k
TOTAL $193k
*May be negative reflecting an increased cost component required to save energy and costs overall

80

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $1,090k 173k
MMBtu
$7.90
- Electrical $750k 14,999k
kWh
$0.065
- Natural Gas $130k 18k
MMBtu
$7.05

249

Implemented Recommendations

3.1

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $24k 2.7k
MMBtu
1.6%
- Electrical $16k 264k
kWh
1.8%
- Natural Gas $4.1k -
MMBtu
-
Waste $2.2k
Productivity/Other $8.4k
TOTAL $35k
*May be negative reflecting an increased cost component required to save energy and costs overall