ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Rolling mill machinery and equipment
3+ Characters Required for Products

7

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $158k 49k
MMBtu
$5.08
- Electrical $78k 1,622k
kWh
$0.052
- Natural Gas $29k 9.2k
MMBtu
$2.64

46

Recommendations

6.6

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $16k 0.8k
MMBtu
1.7%
- Electrical $4.6k 81k
kWh
5.0%
- Natural Gas $8.4k -
MMBtu
-
Waste $1.1k
Productivity/Other $90k
TOTAL $107k
*May be negative reflecting an increased cost component required to save energy and costs overall

7

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $158k 49k
MMBtu
$5.08
- Electrical $78k 1,622k
kWh
$0.052
- Natural Gas $29k 9.2k
MMBtu
$2.64

23

Implemented Recommendations

3.3

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $5.8k 0.6k
MMBtu
1.2%
- Electrical $3.2k 58k
kWh
3.6%
- Natural Gas $0.0k -
MMBtu
-
Waste $0.5k
Productivity/Other $59k
TOTAL $66k
*May be negative reflecting an increased cost component required to save energy and costs overall