The ITAC Statistics page displays the average assessment results for the selected criteria.
| ARC | 2+ Digits Required | |
| NAICS | 3+ Digits Required | |
| SIC | Overhead traveling cranes, hoists, and monorail systems | |
| 3+ Characters Required for Products | ||
13
Matching Assessments
| Initial Plant Size Averages | Costs | Usage | Unit Cost | |
|---|---|---|---|---|
| All Energy | $329k | 54k |
MMBtu
|
$7.01 |
| - Electrical | $149k | 3,326k |
kWh
|
$0.055 |
| - Natural Gas | $96k | 19k |
MMBtu
|
$5.22 |
105
Recommendations
8.1
Recommendations Per Assessment
| Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
|---|---|---|---|---|
| All Energy | $55k | 2.9k |
MMBtu
|
5.4% |
| - Electrical | $16k | 281k |
kWh
|
8.5% |
| - Natural Gas | $30k | - |
MMBtu
|
- |
| Waste | $9.3k | |||
| Productivity/Other | $17k | |||
| TOTAL | $82k | |||
| *May be negative reflecting an increased cost component required to save energy and costs overall | ||||
12
with Implementation Data
| Initial Plant Size Averages | Costs | Usage | Unit Cost | |
|---|---|---|---|---|
| All Energy | $314k | 53k |
MMBtu
|
$6.92 |
| - Electrical | $143k | 3,322k |
kWh
|
$0.054 |
| - Natural Gas | $87k | 19k |
MMBtu
|
$5.04 |
40
Implemented Recommendations
3.3
Implemented Per Assessment
| Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
|---|---|---|---|---|
| All Energy | $12k | 1.8k |
MMBtu
|
3.4% |
| - Electrical | $9.0k | 173k |
kWh
|
5.2% |
| - Natural Gas | $1.1k | - |
MMBtu
|
- |
| Waste | $2.7k | |||
| Productivity/Other | $0.8k | |||
| TOTAL | $16k | |||
| *May be negative reflecting an increased cost component required to save energy and costs overall | ||||