The ITAC Statistics page displays the average assessment results for the selected criteria.
| ARC | 2+ Digits Required | |
| NAICS | 3+ Digits Required | |
| SIC | Oil and gas field machinery and equipment | |
| 3+ Characters Required for Products | ||
102
Matching Assessments
| Initial Plant Size Averages | Costs | Usage | Unit Cost | |
|---|---|---|---|---|
| All Energy | $477k | 136k |
MMBtu
|
$6.94 |
| - Electrical | $294k | 10,850k |
kWh
|
$0.059 |
| - Natural Gas | $93k | 24k |
MMBtu
|
$5.33 |
759
Recommendations
7.4
Recommendations Per Assessment
| Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
|---|---|---|---|---|
| All Energy | $70k | 7.0k |
MMBtu
|
5.2% |
| - Electrical | $42k | 686k |
kWh
|
6.3% |
| - Natural Gas | $13k | - |
MMBtu
|
- |
| Waste | $3.0k | |||
| Productivity/Other | $22k | |||
| TOTAL | $95k | |||
| *May be negative reflecting an increased cost component required to save energy and costs overall | ||||
98
with Implementation Data
| Initial Plant Size Averages | Costs | Usage | Unit Cost | |
|---|---|---|---|---|
| All Energy | $477k | 139k |
MMBtu
|
$6.77 |
| - Electrical | $296k | 11,085k |
kWh
|
$0.058 |
| - Natural Gas | $97k | 25k |
MMBtu
|
$5.19 |
381
Implemented Recommendations
3.9
Implemented Per Assessment
| Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
|---|---|---|---|---|
| All Energy | $43k | 4.4k |
MMBtu
|
3.2% |
| - Electrical | $26k | 430k |
kWh
|
3.9% |
| - Natural Gas | $8.7k | - |
MMBtu
|
- |
| Waste | $1.6k | |||
| Productivity/Other | $11k | |||
| TOTAL | $55k | |||
| *May be negative reflecting an increased cost component required to save energy and costs overall | ||||