ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Construction machinery and equipment
3+ Characters Required for Products

115

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $427k 65k
MMBtu
$7.23
- Electrical $242k 4,245k
kWh
$0.059
- Natural Gas $109k 21k
MMBtu
$5.25

858

Recommendations

7.5

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $64k 5.6k
MMBtu
8.5%
- Electrical $31k 543k
kWh
12.8%
- Natural Gas $12k -
MMBtu
-
Waste $3.7k
Productivity/Other $61k
TOTAL $129k
*May be negative reflecting an increased cost component required to save energy and costs overall

109

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $409k 65k
MMBtu
$6.66
- Electrical $232k 4,247k
kWh
$0.056
- Natural Gas $107k 20k
MMBtu
$5.05

387

Implemented Recommendations

3.6

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $23k 2.4k
MMBtu
3.7%
- Electrical $13k 235k
kWh
5.5%
- Natural Gas $6.0k -
MMBtu
-
Waste $0.7k
Productivity/Other $28k
TOTAL $52k
*May be negative reflecting an increased cost component required to save energy and costs overall