ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Small arms
3+ Characters Required for Products

13

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $450k 55k
MMBtu
$9.08
- Electrical $278k 4,321k
kWh
$0.073
- Natural Gas $67k 10k
MMBtu
$5.10

73

Recommendations

5.6

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $51k 7.0k
MMBtu
12.7%
- Electrical $38k 686k
kWh
15.9%
- Natural Gas $3.2k -
MMBtu
-
Waste $4.3k
Productivity/Other $14k
TOTAL $69k
*May be negative reflecting an increased cost component required to save energy and costs overall

12

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $453k 56k
MMBtu
$9.02
- Electrical $288k 4,381k
kWh
$0.076
- Natural Gas $70k 11k
MMBtu
$4.97

32

Implemented Recommendations

2.7

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $14k 1.7k
MMBtu
3.1%
- Electrical $11k 169k
kWh
3.9%
- Natural Gas $2.2k -
MMBtu
-
Waste $2.5k
Productivity/Other $9.8k
TOTAL $26k