ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Iron and steel forgings
3+ Characters Required for Products

97

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $1,217k 221k
MMBtu
$6.90
- Electrical $511k 9,851k
kWh
$0.30
- Natural Gas $520k 119k
MMBtu
$4.81

767

Recommendations

7.9

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $151k 10k
MMBtu
4.6%
- Electrical $60k 991k
kWh
10.1%
- Natural Gas $60k -
MMBtu
-
Waste $3.6k
Productivity/Other $37k
TOTAL $191k
*May be negative reflecting an increased cost component required to save energy and costs overall

91

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $1,221k 225k
MMBtu
$6.74
- Electrical $505k 9,916k
kWh
$0.32
- Natural Gas $529k 123k
MMBtu
$4.83

342

Implemented Recommendations

3.8

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $47k 3.8k
MMBtu
1.7%
- Electrical $22k 374k
kWh
3.8%
- Natural Gas $15k -
MMBtu
-
Waste $0.9k
Productivity/Other $8.5k
TOTAL $56k
*May be negative reflecting an increased cost component required to save energy and costs overall