ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Iron and steel forgings
3+ Characters Required for Products

91

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $1,183k 214k
MMBtu
$6.84
- Electrical $491k 9,666k
kWh
$0.32
- Natural Gas $509k 114k
MMBtu
$4.85

727

Recommendations

8.0

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $151k 9.7k
MMBtu
4.5%
- Electrical $56k 948k
kWh
9.8%
- Natural Gas $63k -
MMBtu
-
Waste $3.9k
Productivity/Other $39k
TOTAL $194k
*May be negative reflecting an increased cost component required to save energy and costs overall

87

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $1,189k 217k
MMBtu
$6.78
- Electrical $491k 9,736k
kWh
$0.33
- Natural Gas $517k 116k
MMBtu
$4.89

319

Implemented Recommendations

3.7

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $47k 3.7k
MMBtu
1.7%
- Electrical $21k 363k
kWh
3.7%
- Natural Gas $15k -
MMBtu
-
Waste $1.0k
Productivity/Other $8.9k
TOTAL $57k