The ITAC Statistics page displays the average assessment results for the selected criteria.
| ARC | 2+ Digits Required | |
| NAICS | 3+ Digits Required | |
| SIC | Metal doors, sash, frames, molding, and trim manufacturing | |
| 3+ Characters Required for Products | ||
117
Matching Assessments
| Initial Plant Size Averages | Costs | Usage | Unit Cost | |
|---|---|---|---|---|
| All Energy | $333k | 49k |
MMBtu
|
$7.72 |
| - Electrical | $197k | 3,252k |
kWh
|
$0.067 |
| - Natural Gas | $79k | 15k |
MMBtu
|
$4.96 |
893
Recommendations
7.6
Recommendations Per Assessment
| Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
|---|---|---|---|---|
| All Energy | $42k | 4.5k |
MMBtu
|
9.1% |
| - Electrical | $28k | 436k |
kWh
|
13.4% |
| - Natural Gas | $8.5k | - |
MMBtu
|
- |
| Waste | $12k | |||
| Productivity/Other | $52k | |||
| TOTAL | $106k | |||
| *May be negative reflecting an increased cost component required to save energy and costs overall | ||||
113
with Implementation Data
| Initial Plant Size Averages | Costs | Usage | Unit Cost | |
|---|---|---|---|---|
| All Energy | $336k | 50k |
MMBtu
|
$7.47 |
| - Electrical | $200k | 3,330k |
kWh
|
$0.065 |
| - Natural Gas | $81k | 15k |
MMBtu
|
$4.91 |
423
Implemented Recommendations
3.7
Implemented Per Assessment
| Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
|---|---|---|---|---|
| All Energy | $19k | 2.1k |
MMBtu
|
4.1% |
| - Electrical | $13k | 201k |
kWh
|
6.0% |
| - Natural Gas | $3.0k | - |
MMBtu
|
- |
| Waste | $0.9k | |||
| Productivity/Other | $9.5k | |||
| TOTAL | $30k | |||
| *May be negative reflecting an increased cost component required to save energy and costs overall | ||||