ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Steel foundries, not elsewhere classified
3+ Characters Required for Products

76

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $1,684k 273k
MMBtu
$6.61
- Electrical $819k 18,034k
kWh
$0.054
- Natural Gas $376k 79k
MMBtu
$5.35

617

Recommendations

8.1

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $133k 8.6k
MMBtu
3.2%
- Electrical $56k 844k
kWh
4.7%
- Natural Gas $48k -
MMBtu
-
Waste $25k
Productivity/Other $147k
TOTAL $304k
*May be negative reflecting an increased cost component required to save energy and costs overall

74

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $1,662k 271k
MMBtu
$6.58
- Electrical $797k 17,934k
kWh
$0.053
- Natural Gas $372k 78k
MMBtu
$5.39

241

Implemented Recommendations

3.3

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $39k 3.1k
MMBtu
1.1%
- Electrical $18k 301k
kWh
1.7%
- Natural Gas $17k -
MMBtu
-
Waste $2.6k
Productivity/Other $42k
TOTAL $83k
*May be negative reflecting an increased cost component required to save energy and costs overall