ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Steel investment foundries
3+ Characters Required for Products

35

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $673k 328k
MMBtu
$7.54
- Electrical $380k 5,741k
kWh
$0.069
- Natural Gas $185k 266k
MMBtu
$5.61

278

Recommendations

7.9

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $71k 4.2k
MMBtu
1.3%
- Electrical $28k 412k
kWh
7.2%
- Natural Gas $31k -
MMBtu
-
Waste $5.1k
Productivity/Other $109k
TOTAL $185k
*May be negative reflecting an increased cost component required to save energy and costs overall

33

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $673k 342k
MMBtu
$7.53
- Electrical $392k 5,831k
kWh
$0.070
- Natural Gas $177k 279k
MMBtu
$5.54

134

Implemented Recommendations

4.1

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $21k 2.1k
MMBtu
0.6%
- Electrical $14k 203k
kWh
3.5%
- Natural Gas $3.0k -
MMBtu
-
Waste $2.9k
Productivity/Other $53k
TOTAL $77k
*May be negative reflecting an increased cost component required to save energy and costs overall