The ITAC Statistics page displays the average assessment results for the selected criteria.
283
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $1,501k | 269k |
MMBtu
|
$7.08 |
- Electrical | $770k | 16,391k |
kWh
|
$0.11 |
- Natural Gas | $296k | 86k |
MMBtu
|
$5.61 |
2,115
Recommendations
7.5
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $127k | 10k |
MMBtu
|
3.8% |
- Electrical | $64k | 986k |
kWh
|
6.0% |
- Natural Gas | $29k | - |
MMBtu
|
- |
Waste | $13k | |||
Productivity/Other | $86k | |||
TOTAL | $226k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
273
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $1,511k | 273k |
MMBtu
|
$6.97 |
- Electrical | $770k | 16,637k |
kWh
|
$0.11 |
- Natural Gas | $299k | 88k |
MMBtu
|
$5.60 |
897
Implemented Recommendations
3.3
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $42k | 3.9k |
MMBtu
|
1.4% |
- Electrical | $23k | 380k |
kWh
|
2.3% |
- Natural Gas | $9.2k | - |
MMBtu
|
- |
Waste | $2.9k | |||
Productivity/Other | $28k | |||
TOTAL | $72k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |