ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Structural clay products, not elsewhere classified
3+ Characters Required for Products

8

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $775k 203k
MMBtu
$7.58
- Electrical $284k 7,156k
kWh
$0.068
- Natural Gas $403k 130k
MMBtu
$2.28

60

Recommendations

7.5

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $46k 2.0k
MMBtu
1.0%
- Electrical $17k 200k
kWh
2.8%
- Natural Gas $25k -
MMBtu
-
Waste $13k
Productivity/Other $34k
TOTAL $93k
*May be negative reflecting an increased cost component required to save energy and costs overall

8

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $775k 203k
MMBtu
$7.58
- Electrical $284k 7,156k
kWh
$0.068
- Natural Gas $403k 130k
MMBtu
$2.28

30

Implemented Recommendations

3.8

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $17k 1.0k
MMBtu
0.5%
- Electrical $8.5k 93k
kWh
1.3%
- Natural Gas $6.5k -
MMBtu
-
Waste $7.8k
Productivity/Other $24k
TOTAL $49k
*May be negative reflecting an increased cost component required to save energy and costs overall