ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Glass products, made of purchased glass
3+ Characters Required for Products

100

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $640k 163k
MMBtu
$7.59
- Electrical $329k 6,696k
kWh
$0.059
- Natural Gas $135k 35k
MMBtu
$5.00

740

Recommendations

7.4

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $43k 7.0k
MMBtu
4.3%
- Electrical $35k 678k
kWh
10.1%
- Natural Gas ($-1.6)k -
MMBtu
-
Waste $4.9k
Productivity/Other $83k
TOTAL $131k
*May be negative reflecting an increased cost component required to save energy and costs overall

100

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $640k 163k
MMBtu
$7.59
- Electrical $329k 6,696k
kWh
$0.059
- Natural Gas $135k 35k
MMBtu
$5.00

383

Implemented Recommendations

3.8

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $19k 2.4k
MMBtu
1.4%
- Electrical $13k 230k
kWh
3.4%
- Natural Gas $1.9k -
MMBtu
-
Waste $2.8k
Productivity/Other $42k
TOTAL $63k
*May be negative reflecting an increased cost component required to save energy and costs overall