The ITAC Statistics page displays the average assessment results for the selected criteria.
100
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $640k | 163k |
MMBtu
|
$7.59 |
- Electrical | $329k | 6,696k |
kWh
|
$0.059 |
- Natural Gas | $135k | 35k |
MMBtu
|
$5.00 |
740
Recommendations
7.4
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $43k | 7.0k |
MMBtu
|
4.3% |
- Electrical | $35k | 678k |
kWh
|
10.1% |
- Natural Gas | ($-1.6)k | - |
MMBtu
|
- |
Waste | $4.9k | |||
Productivity/Other | $83k | |||
TOTAL | $131k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
100
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $640k | 163k |
MMBtu
|
$7.59 |
- Electrical | $329k | 6,696k |
kWh
|
$0.059 |
- Natural Gas | $135k | 35k |
MMBtu
|
$5.00 |
383
Implemented Recommendations
3.8
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $19k | 2.4k |
MMBtu
|
1.4% |
- Electrical | $13k | 230k |
kWh
|
3.4% |
- Natural Gas | $1.9k | - |
MMBtu
|
- |
Waste | $2.8k | |||
Productivity/Other | $42k | |||
TOTAL | $63k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |