The ITAC Statistics page displays the average assessment results for the selected criteria.
6
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $123k | 21k |
MMBtu
|
$6.48 |
- Electrical | $60k | 1,143k |
kWh
|
$0.065 |
- Natural Gas | $48k | 9.7k |
MMBtu
|
$5.75 |
45
Recommendations
7.5
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $17k | 1.1k |
MMBtu
|
4.9% |
- Electrical | $7.3k | 103k |
kWh
|
9.0% |
- Natural Gas | $6.6k | - |
MMBtu
|
- |
Waste | - | |||
Productivity/Other | ($-0.1)k | |||
TOTAL | $17k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
6
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $123k | 21k |
MMBtu
|
$6.48 |
- Electrical | $60k | 1,143k |
kWh
|
$0.065 |
- Natural Gas | $48k | 9.7k |
MMBtu
|
$5.75 |
28
Implemented Recommendations
4.7
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $9.6k | 0.4k |
MMBtu
|
1.7% |
- Electrical | $2.7k | 36k |
kWh
|
3.1% |
- Natural Gas | $4.0k | - |
MMBtu
|
- |
Waste | - | |||
Productivity/Other | ($-0.1)k | |||
TOTAL | $9.6k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |