The ITAC Statistics page displays the average assessment results for the selected criteria.
1,754
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $647k | 103k |
MMBtu
|
$7.50 |
- Electrical | $451k | 8,803k |
kWh
|
$0.060 |
- Natural Gas | $59k | 12k |
MMBtu
|
$5.32 |
13,492
Recommendations
7.7
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $73k | 9.5k |
MMBtu
|
9.2% |
- Electrical | $55k | 924k |
kWh
|
10.5% |
- Natural Gas | $2.9k | - |
MMBtu
|
- |
Waste | $7.8k | |||
Productivity/Other | $44k | |||
TOTAL | $124k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
1,702
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $633k | 102k |
MMBtu
|
$7.39 |
- Electrical | $442k | 8,708k |
kWh
|
$0.060 |
- Natural Gas | $59k | 12k |
MMBtu
|
$5.29 |
6,164
Implemented Recommendations
3.6
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $26k | 3.5k |
MMBtu
|
3.4% |
- Electrical | $19k | 342k |
kWh
|
3.9% |
- Natural Gas | $2.2k | - |
MMBtu
|
- |
Waste | $2.5k | |||
Productivity/Other | $15k | |||
TOTAL | $44k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |