ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Products of petroleum and coal, not elsewhere classified
3+ Characters Required for Products

7

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $1,911k 426k
MMBtu
$5.00
- Electrical $494k 9,502k
kWh
$0.057
- Natural Gas $1,268k 327k
MMBtu
$4.50

48

Recommendations

6.9

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $388k 43k
MMBtu
10.0%
- Electrical $205k 4,149k
kWh
43.7%
- Natural Gas $174k -
MMBtu
-
Waste $8.6k
Productivity/Other $825k
TOTAL $1,222k
*May be negative reflecting an increased cost component required to save energy and costs overall

7

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $1,911k 426k
MMBtu
$5.00
- Electrical $494k 9,502k
kWh
$0.057
- Natural Gas $1,268k 327k
MMBtu
$4.50

28

Implemented Recommendations

4.0

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $72k 3.6k
MMBtu
0.9%
- Electrical $18k 354k
kWh
3.7%
- Natural Gas $54k -
MMBtu
-
Waste -
Productivity/Other $26k
TOTAL $98k
*May be negative reflecting an increased cost component required to save energy and costs overall