Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $14,896k | 2,441k |
MMBtu
|
$5.17 |
- Electrical | $5,546k | 87,635k |
kWh
|
$0.052 |
- Natural Gas | $8,786k | 1,471k |
MMBtu
|
$4.42 |
155
Recommendations
7.4
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $779k | 12k |
MMBtu
|
0.5% |
- Electrical | $67k | 1,178k |
kWh
|
1.3% |
- Natural Gas | $632k | - |
MMBtu
|
- |
Waste | $1.9k | |||
Productivity/Other | $59k | |||
TOTAL | $840k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
20
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $15,572k | 2,556k |
MMBtu
|
$4.95 |
- Electrical | $5,819k | 91,937k |
kWh
|
$0.052 |
- Natural Gas | $9,225k | 1,545k |
MMBtu
|
$4.64 |
64
Implemented Recommendations
3.2
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $232k | 4.4k |
MMBtu
|
0.2% |
- Electrical | $21k | 428k |
kWh
|
0.5% |
- Natural Gas | $136k | - |
MMBtu
|
- |
Waste | $0.1k | |||
Productivity/Other | $49k | |||
TOTAL | $281k | |||