Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Cyclic organic crudes and intermediates, and organic dyes and pigments
3+ Characters Required for Products

18

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $1,429k 229k
MMBtu
$7.10
- Electrical $517k 9,116k
kWh
$0.066
- Natural Gas $668k 113k
MMBtu
$4.76

135

Recommendations

7.5

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $162k 12k
MMBtu
5.2%
- Electrical $66k 1,160k
kWh
12.7%
- Natural Gas $61k -
MMBtu
-
Waste $2.8k
Productivity/Other $13k
TOTAL $178k
*May be negative reflecting an increased cost component required to save energy and costs overall

18

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $1,429k 229k
MMBtu
$7.10
- Electrical $517k 9,116k
kWh
$0.066
- Natural Gas $668k 113k
MMBtu
$4.76

49

Implemented Recommendations

2.7

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $75k 1.8k
MMBtu
0.8%
- Electrical $12k 173k
kWh
1.9%
- Natural Gas $60k -
MMBtu
-
Waste -
Productivity/Other $1.1k
TOTAL $76k
*May be negative reflecting an increased cost component required to save energy and costs overall