ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Synthetic rubber (vulcanizable elastomers)
3+ Characters Required for Products

19

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $4,021k 884k
MMBtu
$5.64
- Electrical $1,625k 37,431k
kWh
$0.050
- Natural Gas $1,582k 446k
MMBtu
$5.30

131

Recommendations

6.9

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $197k (-0.7)k
MMBtu
(-0.1)%
- Electrical $33k (-68.6)k
kWh
(-0.2)%
- Natural Gas $133k -
MMBtu
-
Waste $21k
Productivity/Other $23k
TOTAL $241k
*May be negative reflecting an increased cost component required to save energy and costs overall

17

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $3,993k 905k
MMBtu
$5.60
- Electrical $1,487k 34,694k
kWh
$0.052
- Natural Gas $1,719k 489k
MMBtu
$5.63

60

Implemented Recommendations

3.5

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $103k 8.4k
MMBtu
0.9%
- Electrical $33k 824k
kWh
2.4%
- Natural Gas $54k -
MMBtu
-
Waste $1.5k
Productivity/Other $4.9k
TOTAL $110k
*May be negative reflecting an increased cost component required to save energy and costs overall