ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Industrial gases
3+ Characters Required for Products

16

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $914k 212k
MMBtu
$6.44
- Electrical $728k 18,710k
kWh
$0.059
- Natural Gas $18k 10k
MMBtu
$4.36

111

Recommendations

6.9

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $98k 15k
MMBtu
7.1%
- Electrical $55k 1,469k
kWh
7.8%
- Natural Gas $0.6k -
MMBtu
-
Waste $3.3k
Productivity/Other $51k
TOTAL $152k
*May be negative reflecting an increased cost component required to save energy and costs overall

16

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $914k 212k
MMBtu
$6.44
- Electrical $728k 18,710k
kWh
$0.059
- Natural Gas $18k 10k
MMBtu
$4.36

48

Implemented Recommendations

3.0

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $69k 10k
MMBtu
4.9%
- Electrical $29k 1,016k
kWh
5.4%
- Natural Gas $0.4k -
MMBtu
-
Waste $2.9k
Productivity/Other $15k
TOTAL $87k
*May be negative reflecting an increased cost component required to save energy and costs overall