The ITAC Statistics page displays the average assessment results for the selected criteria.
154
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $2,223k | 475k |
MMBtu
|
$6.22 |
- Electrical | $1,025k | 26,404k |
kWh
|
$0.053 |
- Natural Gas | $801k | 169k |
MMBtu
|
$6.07 |
1,116
Recommendations
7.2
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $191k | 26k |
MMBtu
|
5.5% |
- Electrical | $110k | 2,560k |
kWh
|
9.7% |
- Natural Gas | $30k | - |
MMBtu
|
- |
Waste | $7.4k | |||
Productivity/Other | $55k | |||
TOTAL | $253k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
146
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $2,215k | 476k |
MMBtu
|
$6.16 |
- Electrical | $1,044k | 26,954k |
kWh
|
$0.052 |
- Natural Gas | $780k | 163k |
MMBtu
|
$6.06 |
472
Implemented Recommendations
3.2
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $83k | 4.4k |
MMBtu
|
0.9% |
- Electrical | $17k | 427k |
kWh
|
1.6% |
- Natural Gas | $50k | - |
MMBtu
|
- |
Waste | $3.4k | |||
Productivity/Other | $24k | |||
TOTAL | $110k | |||