1,207
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $1,452k | 338k |
MMBtu
|
$7.34 |
- Electrical | $652k | 14,534k |
kWh
|
$0.068 |
- Natural Gas | $569k | 176k |
MMBtu
|
$5.53 |
9,104
Recommendations
7.5
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $175k | 16k |
MMBtu
|
4.6% |
- Electrical | $84k | 1,519k |
kWh
|
10.5% |
- Natural Gas | $61k | - |
MMBtu
|
- |
Waste | $12k | |||
Productivity/Other | $55k | |||
TOTAL | $242k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
1,148
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $1,483k | 349k |
MMBtu
|
$7.17 |
- Electrical | $662k | 14,878k |
kWh
|
$0.068 |
- Natural Gas | $588k | 182k |
MMBtu
|
$5.49 |
4,048
Implemented Recommendations
3.5
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $58k | 4.9k |
MMBtu
|
1.4% |
- Electrical | $28k | 477k |
kWh
|
3.2% |
- Natural Gas | $21k | - |
MMBtu
|
- |
Waste | $3.9k | |||
Productivity/Other | $20k | |||
TOTAL | $82k | |||