ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Corrugated and solid fiber boxes
3+ Characters Required for Products

313

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $460k 91k
MMBtu
$6.26
- Electrical $214k 4,007k
kWh
$0.061
- Natural Gas $178k 39k
MMBtu
$4.60

2,552

Recommendations

8.2

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $66k 6.3k
MMBtu
7.0%
- Electrical $37k 616k
kWh
15.4%
- Natural Gas $18k -
MMBtu
-
Waste $8.8k
Productivity/Other $53k
TOTAL $128k
*May be negative reflecting an increased cost component required to save energy and costs overall

308

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $457k 91k
MMBtu
$6.11
- Electrical $213k 4,004k
kWh
$0.060
- Natural Gas $178k 39k
MMBtu
$4.60

1,178

Implemented Recommendations

3.8

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $22k 1.8k
MMBtu
2.0%
- Electrical $9.5k 174k
kWh
4.3%
- Natural Gas $10k -
MMBtu
-
Waste $4.1k
Productivity/Other $14k
TOTAL $40k