ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Paper mills
3+ Characters Required for Products

100

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $4,156k 871k
MMBtu
$6.66
- Electrical $1,773k 42,109k
kWh
$0.066
- Natural Gas $1,279k 267k
MMBtu
$5.30

754

Recommendations

7.5

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $313k 38k
MMBtu
4.4%
- Electrical $137k 3,703k
kWh
8.8%
- Natural Gas $38k -
MMBtu
-
Waste $36k
Productivity/Other $117k
TOTAL $466k
*May be negative reflecting an increased cost component required to save energy and costs overall

99

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $4,190k 878k
MMBtu
$6.66
- Electrical $1,786k 42,452k
kWh
$0.066
- Natural Gas $1,290k 269k
MMBtu
$5.32

372

Implemented Recommendations

3.8

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $141k 4.7k
MMBtu
0.5%
- Electrical $31k 460k
kWh
1.1%
- Natural Gas $35k -
MMBtu
-
Waste $9.5k
Productivity/Other $13k
TOTAL $163k
*May be negative reflecting an increased cost component required to save energy and costs overall