ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Furniture and fixtures, not elsewhere classified
3+ Characters Required for Products

22

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $266k 33k
MMBtu
$8.05
- Electrical $144k 2,078k
kWh
$0.072
- Natural Gas $79k 12k
MMBtu
$6.26

165

Recommendations

7.5

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $50k 5.6k
MMBtu
16.9%
- Electrical $38k 551k
kWh
26.5%
- Natural Gas $5.6k -
MMBtu
-
Waste $1.6k
Productivity/Other $12k
TOTAL $64k
*May be negative reflecting an increased cost component required to save energy and costs overall

21

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $231k 30k
MMBtu
$7.95
- Electrical $112k 1,817k
kWh
$0.070
- Natural Gas $76k 12k
MMBtu
$6.22

90

Implemented Recommendations

4.3

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $19k 2.7k
MMBtu
9.0%
- Electrical $14k 265k
kWh
14.6%
- Natural Gas $2.2k -
MMBtu
-
Waste $0.1k
Productivity/Other $2.5k
TOTAL $21k
*May be negative reflecting an increased cost component required to save energy and costs overall