ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Miscellaneous furniture and fixtures
3+ Characters Required for Products

33

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $281k 40k
MMBtu
$7.79
- Electrical $140k 2,622k
kWh
$0.065
- Natural Gas $84k 13k
MMBtu
$6.69

257

Recommendations

7.8

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $36k 4.1k
MMBtu
10.3%
- Electrical $25k 398k
kWh
15.2%
- Natural Gas $6.6k -
MMBtu
-
Waste $12k
Productivity/Other $21k
TOTAL $69k
*May be negative reflecting an increased cost component required to save energy and costs overall

33

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $281k 40k
MMBtu
$7.79
- Electrical $140k 2,622k
kWh
$0.065
- Natural Gas $84k 13k
MMBtu
$6.69

141

Implemented Recommendations

4.3

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $18k 2.4k
MMBtu
6.2%
- Electrical $13k 237k
kWh
9.1%
- Natural Gas $1.7k -
MMBtu
-
Waste $7.6k
Productivity/Other $6.9k
TOTAL $32k
*May be negative reflecting an increased cost component required to save energy and costs overall