The ITAC Statistics page displays the average assessment results for the selected criteria.
6
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $265k | 36k |
MMBtu
|
$11.41 |
- Electrical | $198k | 3,384k |
kWh
|
$1.49 |
- Natural Gas | $0.1k | 0.0k |
MMBtu
|
$2.08 |
36
Recommendations
6.0
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $54k | 9.5k |
MMBtu
|
26.4% |
- Electrical | $40k | 925k |
kWh
|
27.3% |
- Natural Gas | $1.1k | - |
MMBtu
|
- |
Waste | - | |||
Productivity/Other | $180k | |||
TOTAL | $234k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
6
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $265k | 36k |
MMBtu
|
$11.41 |
- Electrical | $198k | 3,384k |
kWh
|
$1.49 |
- Natural Gas | $0.1k | 0.0k |
MMBtu
|
$2.08 |
13
Implemented Recommendations
2.2
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $13k | 2.1k |
MMBtu
|
5.8% |
- Electrical | $11k | 201k |
kWh
|
6.0% |
- Natural Gas | - | - |
MMBtu
|
- |
Waste | - | |||
Productivity/Other | $162k | |||
TOTAL | $174k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |