ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Apparel and accessories, not elsewhere classified
3+ Characters Required for Products

20

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $175k 26k
MMBtu
$7.67
- Electrical $75k 1,348k
kWh
$0.065
- Natural Gas $58k 12k
MMBtu
$6.03

129

Recommendations

6.5

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $25k 1.9k
MMBtu
7.3%
- Electrical $10k 183k
kWh
13.6%
- Natural Gas $10k -
MMBtu
-
Waste $1.6k
Productivity/Other $8.1k
TOTAL $35k
*May be negative reflecting an increased cost component required to save energy and costs overall

19

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $173k 26k
MMBtu
$7.29
- Electrical $77k 1,362k
kWh
$0.066
- Natural Gas $59k 12k
MMBtu
$5.86

62

Implemented Recommendations

3.3

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $14k 1.0k
MMBtu
3.6%
- Electrical $6.5k 93k
kWh
6.9%
- Natural Gas $5.5k -
MMBtu
-
Waste $0.3k
Productivity/Other $5.5k
TOTAL $19k
*May be negative reflecting an increased cost component required to save energy and costs overall