The ITAC Statistics page displays the average assessment results for the selected criteria.
29
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $979k | 193k |
MMBtu
|
$5.67 |
- Electrical | $503k | 8,707k |
kWh
|
$0.067 |
- Natural Gas | $264k | 64k |
MMBtu
|
$2.63 |
214
Recommendations
7.4
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $102k | 8.0k |
MMBtu
|
4.2% |
- Electrical | $56k | 785k |
kWh
|
9.0% |
- Natural Gas | $43k | - |
MMBtu
|
- |
Waste | $4.5k | |||
Productivity/Other | $12k | |||
TOTAL | $118k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
29
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $979k | 193k |
MMBtu
|
$5.67 |
- Electrical | $503k | 8,707k |
kWh
|
$0.067 |
- Natural Gas | $264k | 64k |
MMBtu
|
$2.63 |
103
Implemented Recommendations
3.6
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $33k | 2.8k |
MMBtu
|
1.4% |
- Electrical | $17k | 272k |
kWh
|
3.1% |
- Natural Gas | $11k | - |
MMBtu
|
- |
Waste | $0.6k | |||
Productivity/Other | $0.3k | |||
TOTAL | $34k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |