The ITAC Statistics page displays the average assessment results for the selected criteria.
432
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $691k | 110k |
MMBtu
|
$7.71 |
- Electrical | $364k | 6,015k |
kWh
|
$0.070 |
- Natural Gas | $202k | 44k |
MMBtu
|
$4.69 |
3,077
Recommendations
7.1
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $76k | 6.5k |
MMBtu
|
5.9% |
- Electrical | $49k | 639k |
kWh
|
10.6% |
- Natural Gas | $12k | - |
MMBtu
|
- |
Waste | $5.8k | |||
Productivity/Other | $57k | |||
TOTAL | $139k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
416
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $693k | 112k |
MMBtu
|
$7.42 |
- Electrical | $364k | 6,109k |
kWh
|
$0.068 |
- Natural Gas | $201k | 45k |
MMBtu
|
$4.50 |
1,399
Implemented Recommendations
3.4
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $30k | 2.8k |
MMBtu
|
2.5% |
- Electrical | $19k | 273k |
kWh
|
4.5% |
- Natural Gas | $5.1k | - |
MMBtu
|
- |
Waste | $2.1k | |||
Productivity/Other | $24k | |||
TOTAL | $56k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |