The ITAC Statistics page displays the average assessment results for the selected criteria.
428
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $686k | 111k |
MMBtu
|
$7.63 |
- Electrical | $364k | 6,057k |
kWh
|
$0.069 |
- Natural Gas | $199k | 44k |
MMBtu
|
$4.64 |
3,053
Recommendations
7.1
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $75k | 6.5k |
MMBtu
|
5.9% |
- Electrical | $48k | 638k |
kWh
|
10.5% |
- Natural Gas | $11k | - |
MMBtu
|
- |
Waste | $5.9k | |||
Productivity/Other | $57k | |||
TOTAL | $138k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
409
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $668k | 110k |
MMBtu
|
$7.26 |
- Electrical | $352k | 5,967k |
kWh
|
$0.067 |
- Natural Gas | $199k | 44k |
MMBtu
|
$4.49 |
1,374
Implemented Recommendations
3.4
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $29k | 2.7k |
MMBtu
|
2.5% |
- Electrical | $18k | 263k |
kWh
|
4.4% |
- Natural Gas | $5.2k | - |
MMBtu
|
- |
Waste | $2.1k | |||
Productivity/Other | $18k | |||
TOTAL | $49k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |