Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Beverages
3+ Characters Required for Products

473

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $834k 133k
MMBtu
$9.19
- Electrical $423k 6,964k
kWh
$0.16
- Natural Gas $219k 42k
MMBtu
$5.95

3,581

Recommendations

7.6

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $100k 7.9k
MMBtu
5.9%
- Electrical $61k 771k
kWh
11.1%
- Natural Gas $19k -
MMBtu
-
Waste $32k
Productivity/Other $47k
TOTAL $178k
*May be negative reflecting an increased cost component required to save energy and costs overall

442

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $764k 127k
MMBtu
$8.88
- Electrical $397k 6,577k
kWh
$0.17
- Natural Gas $213k 41k
MMBtu
$5.82

1,622

Implemented Recommendations

3.7

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $34k 3.1k
MMBtu
2.4%
- Electrical $21k 301k
kWh
4.6%
- Natural Gas $9.2k -
MMBtu
-
Waste $5.1k
Productivity/Other $21k
TOTAL $60k
*May be negative reflecting an increased cost component required to save energy and costs overall