ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Animal and marine fats and oils
3+ Characters Required for Products

17

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $1,811k 456k
MMBtu
$6.25
- Electrical $519k 10,590k
kWh
$0.069
- Natural Gas $984k 333k
MMBtu
$3.57

110

Recommendations

6.5

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $134k 8.2k
MMBtu
1.8%
- Electrical $59k 804k
kWh
7.6%
- Natural Gas $25k -
MMBtu
-
Waste $55k
Productivity/Other $99k
TOTAL $288k
*May be negative reflecting an increased cost component required to save energy and costs overall

15

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $1,972k 510k
MMBtu
$5.91
- Electrical $513k 11,390k
kWh
$0.060
- Natural Gas $1,110k 376k
MMBtu
$3.76

42

Implemented Recommendations

2.8

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $55k 2.1k
MMBtu
0.4%
- Electrical $9.7k 204k
kWh
1.8%
- Natural Gas $13k -
MMBtu
-
Waste $13k
Productivity/Other $2.2k
TOTAL $70k
*May be negative reflecting an increased cost component required to save energy and costs overall