The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC | 2+ Digits Required | |
NAICS | 3+ Digits Required | |
SIC | Vegetable oil mills, except corn, cottonseed, and soybean | |
3+ Characters Required for Products |
4
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $292k | 31k |
MMBtu
|
$15.63 |
- Electrical | $199k | 2,356k |
kWh
|
$0.13 |
- Natural Gas | $29k | 6.7k |
MMBtu
|
$7.66 |
29
Recommendations
7.3
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $72k | 3.8k |
MMBtu
|
12.1% |
- Electrical | $55k | 367k |
kWh
|
15.6% |
- Natural Gas | $6.7k | - |
MMBtu
|
- |
Waste | - | |||
Productivity/Other | ($0.0)k | |||
TOTAL | $72k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
3
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $208k | 28k |
MMBtu
|
$16.40 |
- Electrical | $145k | 1,820k |
kWh
|
$0.15 |
- Natural Gas | $38k | 9.0k |
MMBtu
|
$10.21 |
5
Implemented Recommendations
1.7
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $15k | 0.5k |
MMBtu
|
1.8% |
- Electrical | $11k | 49k |
kWh
|
2.7% |
- Natural Gas | $4.0k | - |
MMBtu
|
- |
Waste | - | |||
Productivity/Other | ($-0.4)k | |||
TOTAL | $15k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |